South Africa: the Port of Durban
The south point of our four corridors. South Africa's busiest container port, read from free radar and optical satellite passes, with this week's public status beside it.

What the satellites saw over Durban, last 90 days
| Reading | Value |
|---|---|
| Radar passes (Sentinel-1, sees through cloud) usable over the box | 19 of 19 |
| Optical scenes (Sentinel-2) with a usable view after the pixel cloud mask | 56 of 88, on 14 days |
| Median whole-tile cloud | 65.8 percent |
| Window | 22 Aug 2026 to 20 Nov 2026 |
What is happening at the port
These are public statements with their dates. They are not Africa Flying measurements.
| Component | Public status | Source |
|---|---|---|
| Durban Gateway Terminal (Pier 2) | Operated under a 25-year arrangement from 1 January 2026 | Parliament reply NW5320 |
| Backlog measures, 18 Nov 2026 | Berth 102 set aside for geared vessels; more vessels diverted to Ngqura; trains made available to move import containers to Gauteng | Transnet media statement, 18 Nov 2026 |
| Pier 1 cranes | Final refurbished ship-to-shore crane scheduled for commissioning on 20 Nov 2026 and handover to operations on 21 Nov 2026, giving six cranes (as stated 18 Nov) | Transnet media statement, 18 Nov 2026 |
| Ngqura container terminal | Private participation in project preparation (23 Oct 2026) | Parliament reply NW5449 |
| Richards Bay dry bulk terminal | In procurement; request for quotations closed 30 Oct 2026 | Parliament reply NW5449 |
| Freight rail access | Third-party access allocated on six corridors in 2026, including the coal line to Richards Bay and the Sishen-Saldanha iron-ore line | Railway Gazette, Apr 2026 |
| Solar, Bid Window 7 | 3,940 MW across 18 solar PV projects; the first reached financial close in April 2026 | Minister reply NW5144 and IPP Office lists |
Ngqura and Richards Bay
Two more port boxes, traced from OpenStreetMap on 21 Nov 2026 (ODbL). They are not in the daily pass list. Each box is the named terminal, plus piers within 500 m at Ngqura, padded outward to the next 0.01 degree. These pictures are not a measurement of the public status table above.